Highway 20 (North Street) Rehabilitation Project

Click here for information about the WIS Hwy 20 Rehabilitation Project

Update 05/20/2024

With progress being made this week with the storm sewer installation, the County ES south leg closure at WIS 20 is scheduled for Wednesday, May 1st. See flyer for details. Message boards will go up on Monday to alert drivers to the anticipated closure and hopefully allow everyone to find an alternate route.
 
Traffic:
1) Access to Dollar General is available by using the median opening by McDonald’s/Shell and using the WIS 20 EB lanes to get to their driveway.
2) During the County ES closure, WIS 20 will remain open for access.
3) Potential re-opening on Monday night if pavement markings can be installed (weather depended)
Last Week:
1) Finished fine grading the gravel
2) Started and completed asphalt paving around County ES. Work on WIS 20 to continue next week between County ES and County L.
3) Install some of the traffic signal bases
This Week:
1) Re-open the intersection
2) Asphalt paving east of County ES
3) Backfill behind curb
4) Prep for sidewalk
5) Shouldering
Rough Schedule of County ES: (very weather dependent on exact date)
- 5/20 – Begin/completed Pavement Marking
- Re-open County ES when the marking is completed (tentatively scheduled for the night of 5/20. Will send a specific update out when schedule is known.
WIS 83 Work - Waterford
WIS 83 Traffic:
1) Work is going to be performed using flagging operations and drums to delineate traffic when each operation is completed. Some minor delays should be expected with the flagging operations.
Rough Schedule for Operations:
- 5/21 – Install new signposts and other sign changes
- 5/23 – Construct the gravel shoulders.
- 5/23/24 – Pick up the drums.